The information on this website should be read in conjunction with the Gabriel Resources news release dated January 20, 2015 which addresses the dispute with Romania regarding the development of the Roşia Montană gold and silver project and the subsequent news release dated July 21, 2015 which announces that Gabriel Resources has filed a Request for Arbitration before the World Bank's International Centre for Settlement of Investment Disputes ("ICSID") against Romania pursuant to the agreements between the Government of Romania and each of the Government of Canada and the Government of the United Kingdom of Great Britain and Northern Ireland for the Promotion and Reciprocal Protection of Investments. For a link to the press release, please click here.

Press releases
See all articles

  • Gabriel files for international arbitration against Romania

    21.07.2015

    Gabriel Resources Ltd. (“Gabriel” or the “Company”) announces that today it has filed a request for arbitration before the World Bank's International Centre for Settlement of Investment Disputes ("ICSID") against Romania (“Request for Arbitration”). This action relates to the Company’s dispute with Romania over the development of the Roşia Montană gold and ...
    Read more
  • Roșia Montană Gold Corporation starts a new collective layoff wave

    01.04.2015

    Roşia Montană Gold Corporation (RMGC) has notified both the “Future of Mining” Trade Union and the labor authorities on the initiation of the collective layoff procedure for a percentage of approximately 35% of the remaining employees of the company, with the final number being determined after the completion of the negotiations with the trade union. Thus, one year after the collective layoffs in ...
    Read more
  • 70% of the employees of Roșia Montană Gold Corporation start technical unemployment

    16.02.2015

    Starting 17 February 2015, 70% of the Roșia Montană Gold Corporation (RMGC) employees will enter a phase of technical unemployment based on temporary suspension of their employment contracts for an indeterminate period. The technical unemployment measure is due to the continuing uncertainty with regard to the authorisation timeline of the Rosia Montana mining project (Project), requiring further action to reduce ...
    Read more
00

Project
stages
Roșia
Montană

Operation

Completion of mine construction and beginning of mining operations. Mining will begin only in Carnic pit this year. In year 0 the storage of the ore with a low consistency in gold and silver, in a low grade ore stockpile, will also take place.

01

Project
stages
Roșia
Montană

Operation

Cetate pit opens, while the activity in Carnic open pit continues.

02

Project
stages
Roșia
Montană

Operation

Mining in Carnic and Cetate pits, opened in the previous years.

03

Project
stages
Roșia
Montană

Operation

Mining in Carnic and Cetate pits, opened in the previous years.

04

Project
stages
Roșia
Montană

Operation

Mining in Carnic and Cetate pits, opened in the previous years.

05

Project
stages
Roșia
Montană

Operation | Rehabilitation

Mining in Cetate pit temporarily stops. Mining in Carnic pit continues.

06

Project
stages
Roșia
Montană

Operation | Rehabilitation

Mining activities only in Carnic pit.

07

Project
stages
Roșia
Montană

Operation

Mining of Carnic pit continues, while Orlea pit is opened for mining as well.

08

Project
stages
Roșia
Montană

Operation

Mining in Carnic and Orlea pits.

09

Project
stages
Roșia
Montană

Operation | Rehabilitation

Mining in Carnic and Orlea pits continues, while Cetate pit is reopened. The 4th pit, Jig, is also opened. Year 9 is the last year of mining in Carnic pit. The pit operations will take place alternatively, in order to optimize the closure plan and reduce the surface impacted by the mining activities.

10

Project
stages
Roșia
Montană

Operation | Rehabilitation

Mining operations continue in Cetate, Orlea and Jig pits, alternatively, to minimize the project impact and facilitate the efficient application of the closure plan.

11

Project
stages
Roșia
Montană

Operation | Rehabilitation

Mining operations continue in Cetate, Orlea and Jig pits. Last year of mining in Jig pit. The operations are done alternatively, to minimize the project impact and facilitate the efficient application of the closure plan.

12

Project
stages
Roșia
Montană

Operation | Rehabilitation

Mining operations continue in Cetate and Orlea pits. This is the last year of mining in the Orlea pit.

13

Project
stages
Roșia
Montană

Operation | Rehabilitation

Cetate pit alone remains open in year 13.

14

Project
stages
Roșia
Montană

Operation | Rehabilitation

This is the last year of pit operations. Mining takes place only in Cetate pit. At the same time, the mining of the depleted ore stockpile begins.

15

Project
stages
Roșia
Montană

Operation | Rehabilitation

Mining of the depleted ore stockpile continues in Year 15.

16

Project
stages
Roșia
Montană

Operation | Rehabilitation

Year 16 is the last year of mining operations. Mining is done only in the depleted ore stockpile.

17

Project
stages
Roșia
Montană

Rehabilitation

Rehabilitation and re-vegetation are completed for the Orlea pit and the tailings dam. Rehabilitation and re-vegetation of the depleted ore stockpile begins, while flooding of the Cetate pit continues. The land related to Jig pit, which has been rehabilitated, re-enters the agricultural circuit this year.

18

Project
stages
Roșia
Montană

Rehabilitation

Rehabilitation and re-vegetation of the depleted ore stockpile and the access roads are completed. Rehabilitation of the process plant and of the tailings dam begins. The land related to the Carnic pit re-enters the agricultural circuit and flooding of the Cetate open pit continues.

19

Project
stages
Roșia
Montană

Rehabilitation

Rehabilitation and re-vegetation are completed for the process plant, the Cetate dam and the secondary retention dam, as well as the aggregates quarries (Sulei and Paraul Porcului). Rehabilitation of the tailings dam and flooding of the Cetate pit continue. The lands related to the tailings dam and the Orlea pit re-enter the agricultural circuit.

20

Project
stages
Roșia
Montană

Rehabilitation

Rehabilitation of the tailings management facility and flooding of the Cetate pit continue. The lands related to the depleted ore stockpile, Carnic, Cetate stockpiles and the aggregates quarries (Sulei and Paraul Porcului) re-enter the agricultural circuit.

21

Project
stages
Roșia
Montană

Rehabilitation

Rehabilitation of the tailings management facility and flooding of the Cetate pit continue. The lands related to the process plant, access roads, Cetate dam and the secondary retention dam re-enter the agricultural circuit.

22

Project
stages
Roșia
Montană

Rehabilitation

Rehabilitation of the tailings management facility and flooding of the the Cetate pit continue.

23

Project
stages
Roșia
Montană

Rehabilitation

Rehabilitation of the tailings management facility and flooding of the Cetate pit continue.

24

Project
stages
Roșia
Montană

Rehabilitation

Rehabilitation of the tailings management facility and flooding of the Cetate pit continue.

25

Project
stages
Roșia
Montană

Rehabilitation

Rehabilitation of the tailings dam continues, as well as water treatment in the Cetate pit, until it complies with the quality requirements for surface waters. The tailings management facility re-enters the agricultural circuit. Starting with year 25, for a period estimated at between 30 and 50 years, post-closure monitoring continues.

Note: This planning is only indicative, as the actual duration and sequence of events will be further improved and detailed during the operation phase, being completed before the implementation of the closure program. All the rehabilitation activities included in this plan are to be carried out by RMGC.